Gellerups Skygger Project Plan

Gellerups Skygger Project Plan

June 2024

  • Initial planning meeting between Teater Animisme technical team and venues, Bevægelseshuset and Gellerup Biblioteket
  • Confirm and plan workshops with group leaders, BABA, Bydels Mødre, Bydels Mødre older peoples group, FGU Rap, Brabrand Billedskole and Cirkus Tværs
  • GDPR forms created for workshop participants
  • 1 day planning meeting, Teater Animisme artistic team
  • PR for workshops designed and distributed

August 2024

  • 1 week testing and experimenting with projection techniques and filming methods, Teater Animisme artistic team at Teater Refleksion

September 2024

  • Workshops with groups, BABA, Bydels Mødre, Bydels Mødre older peoples group, FGU Rap, Brabrand Billedskole and Cirkus Tværs
  • Sampling of musicians and voices at corresponding workshops
  • Photography of one workshop for PR

October 2024

  • 3 days of drop in workshops at Gellerup Biblioteket and City Vest
  • 3 weeks shadow puppet and storyboard development
  • 2 weeks sound track composition
  • PR campaign begins
  • Second planning meeting between Teater Animisme technical team and venues, Bevægelseshuset and Gellerup Biblioteket

November 2024

  • 2 weeks filming shadow puppetry at Teater Refleksion

December 2024

  • 4 weeks postproduction editing the films and mapping projections
  • 2 weeks technical development, designing and building housing for projectors for use in outdoors and distribution of sound and electrical equipment
  • 1 meeting at Verdens Pladsen testing projection system

January 2025  

  • 01.25 – 17.01.25 1 week set up and testing of installation
  • 01.2025 Opening event
  • Photography of installation for PR
  • The installation will play approximately kl. 07:00 – Kl. 8:00 and kl. 17 – Kl. 19, shifting times as day light hours change
  • The installation will be run from a computer that starts and stops playing automatically
  • Installation will be monitored and maintained by the Teater Animisme artistic team

February 2025

  • February 2025 installation closes
  • February 2025 installation is dismantled and removed

March 2025

  • Evaluation, budget reviewed, reports submitted